Construction of gas pipeline 55 km Tagrinskoye field
-
Realization period2016-2017
-
CustomerOOO Sibhimservis, JSC Zagorsk Pipe Plant
-
ManufacturerJSC Vyksa Metallurgical Plant
-
Area of activityOil and Gas Department
Description
Construction of a 55 km long gas pipeline in double-layer insulation, diameter – 720 mm, pressure – 7 bar (excess). for feeding gas into the gas pipeline of PJSC SIBUR.
Supply of large-diameter electric-welded pipes 720*8 for the construction of a 55 km long gas pipeline from the Tagrinskoye field in the Khanty-Mansiysk Autonomous Okrug to the Varyeganskaya compressor station with a capacity of 0.7 billion cubic meters of gas per year.
Pipes manufactured by OMK and ZTZ in the northern version for an operating pressure of 1.6 MPa with a factory double-layer external anti-corrosion polyethylene coating according to TU 1394-015-05757848-2005
Supply of auxiliary equipment: shut-off valves, underground tanks, pipeline components, launch and receiving chamber devices, support and guide rings
Area of operating activities: Western Siberia.